Section of Coffee Creek Road closed during work to upgrade culvert infrastructure

Work to replace the aging and damaged culvert infrastructure on Coffee Creek Road will restrict traffic between Kelly Road and Santa Fe Avenue during the project.

Because of the impact of recent rains, that section of road – more on the western end of the section of Coffee Creek between Kelly and Santa Fe – currently is closed to through traffic and will remain that way through the completion of the project. Access into neighborhoods in that area on either side of the project will remain available.

Preliminary work on preparing the culvert for the project is underway, and work to complete removal and begin the upgrade on the culvert will begin on June 13. Completion of the culvert repairs and upgrade, as well as work to repair the road in that location, is expected to take 30 to 60 days, with cooperative weather.

###